Case study5 min read8 July 2026Examin Field Operations

How a commercial construction site reached 98.2 % PPE compliance in 90 days

A commercial construction project (a logistics facility, roughly 140 workers across nine subcontractors at peak) ran Examin's safety module across 18 zones for its structural phase. The compliance curve from 71 % to 98.2 % is the headline; what happened around it is the useful part.

The starting point

Safety management by walkaround: two site supervisors covering 18 active zones, incident reporting that was honest but late, and a general contractor under pressure from both its insurer and a client with a public safety pledge. Sixteen existing site cameras (a mix of fixed and pole-mounted PTZ) were recording for security and being used for nothing else.

The deployment

  • Week 1: silent baseline. Detection on, alerts off. Helmet-plus-hi-vis compliance measured at 71 %, with clear patterns: the post-lunch half hour and two specific zones accounted for a disproportionate share of violations.
  • Weeks 2 and 3: tuned alerting. Per-zone rules (welding bay needs face shields, office corridor needs nothing), an 8-second grace timer, and routing to the responsible zone supervisor's phone rather than a central screen.
  • Weeks 4 to 13: steady state. Weekly trend reports by zone and subcontractor, shared in the site's coordination meeting.

The curve

71 % at baseline, 84 % two weeks after alerts went live, 89 % at day 45, 95 % at day 70, 98.2 % at day 90, with a median violation-to-alert time of 38 seconds. The mechanism was immediacy: a supervisor speaking to a specific person about a specific moment, minutes after it happened, with the frame on their phone. The weekly subcontractor scoreboard did the rest; no subcontractor stayed at the bottom of it for two weeks in a row.

Beyond PPE

Vehicle-pedestrian proximity detection surfaced 5 to 7 near-miss events per week in one yard corner that had never produced a single incident report. A painted walkway and one relocated material stack took the count to zero. The insurer's engineering review noted the near-miss program specifically; the general contractor reports a measurable effect on its premium discussion, though the renewal postdates this study.

In their words

"I was promised a dashboard and braced for a toy. What I got was thirty extra pairs of eyes that never blink and never exaggerate. My supervisors stopped arguing about what happened, because we can just look." HSE lead, general contractor

What made it work

The silent baseline created the mandate, the per-zone tuning kept alerts credible, and routing to zone supervisors made the system a tool rather than surveillance. The day-by-day tuning notes are in our 90-day field notes, and the capability set is on the Health & Safety page.

Related modules

Deployment window open

Put your cameras to work.

A 30-minute walkthrough on your own footage. See what the vision core finds on day one.